1Locate
BC 1 Call has the utilities marked in paint and flags: yellow for gas, blue for water, orange for communications. White paint outlines the cut. Nothing digs until every mark is checked.
2Strip topsoil
The dark organic layer comes off first and is stockpiled on the lot for the landscaper. It can’t carry a footing, but it’s worth keeping.
3Excavate
We dig to the surveyor’s grade, checking depth against a laser as we go. Spoil sits at least 1.2 m back from the edge, and any marked line near the cut is exposed by hand first.
4Bench & shore
Past 1.2 m, nobody steps in until the walls are safe. Open sides are benched back in steps, and beside the neighbour’s footing the engineer’s shoring holds the face.
5Backfill & compact
Once the foundation and drain tile are in and inspected, drain rock and fill go back in 300 mm lifts, each one compacted before the next is placed.
LocateBC 1 Call has the utilities marked in paint and flags: yellow for gas, blue for water, orange for communications. White paint outlines the cut. Nothing digs until every mark is checked.